A cable costing 500 million euros was laid to bypass the “grave” of Dobby from “Harry Potter”


Engineers route the Greenlink energy cable around the Dobby memorial at Freshwater West beach in Wales.

Energy project route costing approx. 500 million euros had to change due to an unexpected obstacle: The “grave” of Dobby, the house elf from the Harry Potter films.

It’s about energy connection Greenlink, which links the power systems of Great Britain and Ireland.

Cable length approx. 190 km and power 500 MW runs under the Irish Sea and underground, connecting County Wexford in Ireland with Pembrokeshire in Wales. The project began work in 2025.

However, a problem arose during the design phase that was probably not on any standard engineering checklist.

The original route was near the beach Freshwater West in Wales. It was here that the scene of Dobby’s death and burial in the film Harry Potter and the Deathly Hallows was filmed.

Following the film’s release, fans turned the site into an unofficial memorial. Visitors leave stones, notes and other small memorial items there.

When it became known that the power cable could pass through the area associated with the character’s “grave”, the developers began to receive complaints.

According to project manager Simon Ludlam, after the publication of information about the route, the company received hundreds of requests from Harry Potter fans. At first, he reportedly didn’t even understand who Dobby was or why the matter was so serious.

But colleagues quickly explained the cultural significance of the place.

As a result, they decided to change the cable route so as not to affect the fan memorial.

The story took on an even more British flavor after it emerged that the new version of the route was closer to real archaeological sites of the Bronze Age, whose age is estimated at approximately 3000 years. They also had to be taken into account when carrying out the work.

Greenlink itself confirms that the cable exit to the shore is located at Freshwater West, and laying under the beach and dunes was carried out using horizontal directional drilling to minimize the impact on the territory.

As a result, a real infrastructure project worth hundreds of millions of euros had to be adapted for the sake of a place that exists thanks to a fictional character.

It’s rare that the influence of popular culture can literally be seen on a map of Europe’s energy infrastructure.



Source link