In the Chinese city of Qingdao ended key stage in the construction of the longest underwater road tunnel in the world: The tunneling shield has completed work on the northern line of the second tunnel under Jiaozhou Bay.
The completion of shield tunneling was announced July 14, 2026. However, this does not yet mean the end of all construction, much less the opening of the tunnel to automobile traffic.
According to Chinese state media, the project's readiness exceeds 70%and it is planned to be completely completed in 2028.
Content
- What stage of construction has been completed?
- Dimensions and structure of the tunnel
- Why is construction considered unique?
- How Qingdao's transport system will change
- The first tunnel under the bay
The excavation is completed, but not the entire tunnel
Initial reports from several media outlets stated that China had allegedly completed the construction of the 17.48 km long tunnel. Actually ended shield penetration of the northern main line.
The giant tunnel boring machine reached the calculated point of dividing the sections, after which the stage of mechanized laying of the main tunnel was officially declared complete.
The builders still have to complete other sections, connecting galleries, road surfaces, utilities, lighting, ventilation, fire safety and traffic control systems.
Therefore, it is premature to call the facility already built and ready for operation. Humanity has not yet learned to distinguish between the end of excavation and the opening of a road, although between them there are usually years of work and a huge amount of concrete.
China has completed the construction of the world's longest underwater tunnel for automobiles.
The total length of the tunnel will be 17.48 km, with 9.95 km running under the Jiaozhou Bay. The project is more than 70% complete. The tunnel is scheduled to open in 2028 in the city… pic.twitter.com/sq6gYxmETS
– ???????? ????? (@SprinterPress) July 15, 2026
The tunnel is 17.48 kilometers long
The second tunnel under Jiaozhou Bay will connect central Qingdao with the Huangdao area and the western coast of the bay.
Main characteristics of the project:
- total length of transport connection – 17.48 km;
- length of the main tunnel section – 14.37 km;
- length under the seabed – 9.95 km;
- design speed – 80 km/h;
- two main transport pipes;
- separate central service tunnel;
- three lanes in each direction.
After commissioning, the facility must become the longest underwater road tunnel in the world in total length and one of the largest structures of this type.
It should be taken into account that world records differ depending on the calculation method: the total length of the tunnel, the length directly under water, the depth or diameter of the tunnel.
Combination of two penetration methods
Construction is carried out using two technologies at once: drilling and blasting method and mechanized shield tunneling.
The most complex northern shield section is about 3.26 km long. To lay it, a specially developed tunnel boring machine “Shenlan” – “Deep Blue Sea” – was used.
The diameter of the tunneling shield is 15.63 meters. The machine not only developed the rock, but also simultaneously installed reinforced concrete segments that formed the hermetic shell of the tunnel.
The main difficulties of the project were related to:
- high sea water pressure;
- hard rocks;
- geological faults;
- heterogeneous soil;
- the need for excavation at great depths;
- risk of water entering the tunnel.
The maximum depth of the main tunnels reaches approximately 95 meters. The equipment was designed to operate at static water pressures of up to 12 bar. Such conditions require constant monitoring of pressure, rock deformations and the tightness of mounted structures.
Why did tunneling take a special place in the project?
The tunnel boring machine was moving through difficult areas of hard rock and zones of geological disturbances, where the usual speed of work is sharply reduced.
Engineers had to develop a system for changing cutting elements under pressure, improve the removal of destroyed rock and ensure the stability of the shield when passing through heterogeneous layers.
A separate problem was the exit of the vehicle from the coastal area under the seabed with a relatively small thickness of the soil above the tunnel. An error in calculations could lead to seawater intrusion or surface instability.
Completion of this stage means that one of the most technically risky parts of the project has been completed successfully.
Safety under sea
After completion of construction work, the tunnel will be equipped with a set of security systems.
It is expected to install:
- constant video surveillance;
- automatic fire and smoke detection;
- exhaust gas removal systems;
- emergency lighting;
- communication with the dispatch center;
- transverse evacuation crossings;
- fire water supply;
- sensors for the condition of structures and water flow.
The central service tunnel will be used for equipment operation, maintenance and emergency evacuation.
What will change for Qingdao
Qingdao is located on both sides of Jiaozhou Bay. The city is home to millions of people, and its port is one of China's largest transport hubs.
The new tunnel should improve connections between the city's central areas and the west coast, where industrial enterprises, port facilities and new residential areas are located.
Once opened it will allow you to:
- reduce travel times across the bay;
- unload the existing underwater tunnel;
- reduce the load on the Bay Bridge;
- speed up the delivery of goods between port areas;
- strengthen the economic integration of the eastern and western parts of Qingdao.
The tunnel will be designed not only for passenger cars, but also for the movement of some medium-tonnage freight transport.
Second tunnel under the bay
This is not Qingdao's first underwater road tunnel. The first tunnel under Jiaozhou Bay was opened in 2011.
Its total length is about 7.8 km, of which approximately 3.95 km are under the sea. It also has three lanes in each direction.
The growth of population, traffic and port economy gradually increased the load on the existing connection, so the authorities decided to build a second, much longer route.
Once the new facility opens, Qingdao's transportation system will include two underwater tunnels, a bay bridge, an expressway and other road connections.
When will the cars go through the tunnel?
The exact opening date has not yet been announced. According to the latest official reports, the project is expected to be fully completed in 2028.
Before this, builders will have to connect all sections, install transport pipes and conduct comprehensive tests of ventilation, electrical supply, fire protection and emergency response systems.
Thus, China has not completed the construction of the entire tunnel, but one of its main and most difficult stages.
Nevertheless, the scale of the event does not become smaller: the main part of the future road has already been laid under the seabed, which, upon completion, should set a new world record for underwater road tunnels.
More Stories
EU candidate fails bottle test
The right to die: the French Parliament adopted a historic law
Minting began in the USA "gold" dollar with Trump portrait